Excavations continued at the Alamo Church last week. Archaeologists completed excavations in EUs 43, 55, and 58. Excavations started in EUs 74, 82, and 83. EU-43 completed final unit documentation last week. The east wall of the unit was identified as the previously documented concrete foundation. This has been recorded in adjacent units, and in several units along the east wall of the church. Final unit documentation entailed photos, maps, and geo scans. Excavation terminated at 110 cm below surface. Excavations in EU-55 concluded last week. The southern half of the unit was a previously excavated and backfilled unit. Because of this, archaeologists only needed to excavate the northern half of EU-55. Soils within EU-55 were representative of construction-related deposits. Archaeologists...